DESCRIPTION

950 Rose Avenue is the address of a new 36,000 sf Recreational Equipment, Inc. (REI) store.  The store will feature a rustic yet modern design utilizing reclaimed wood and brick and contemporary vertical and etched metal paneling.  Entrances will be framed by large wood and steel trellises.

CHALLENGE

Subsurface conditions at the site consisted of 3 to 14 ft of soft to medium-stiff clay fill, loose to medium dense silt and silty sands to depths of 30 ft, and decomposed rock.

The fill soils were easily improved using Geopier Rammed Aggregate Pier® elements to support the building foundations.  However, the real challenge was to develop a cost-effective way to limit differential settlement where the REI store connected to an adjoining 19-story tower supported on drilled shafts bearing on rock.

SOLUTION

The geotechnical engineer recommended the use of Geopier Rammed Aggregate Pier® elements to improve the fill soils so they could support footings designed for 6,000 psf for the main portion of the REI store.

For the interface with the 19-story tower, Ductile Iron Piles driven to decomposed rock were selected to support the loads from the south wall of the REI store adjacent to the tower.   This approach eliminated the differential settlement concern at the interface between the two buildings.

GeoStructures, Inc. installed 159, 30-inch Geopier® elements to provide ground improvement across the majority of the site and 38 Ductile Iron Piles along the south wall of the store.  Being able to work with one design/build contractor that could deliver multiple solutions allowed the team to provide a complete foundation system solution economically and on schedule.

Pike and Rose-01

The Ductile Iron Pile solution consisted of 118 mm diameter piles with 7.5 mm wall thickness designed to terminate on decomposed rock.  The piles were designed for a working load of 40 tons.

A total of 38 Ductile Iron Piles were installed in 2 days.  Pile lengths ranged from 27 to 58 ft.

Photo-3

Photo-2

Photo-1

Owner

Federal Realty Investment Trust - Rockville, MD

Construction Manager

LF Jennings, Inc - Falls Church, VA

Architect

Callison RTKL, Inc - Washington, DC

Structural Engineer

Armour Unsderfer Engineering - Bellevue, WA

Geotechnical Engineer

ECS Mid-Atlantic, LLC - Frederick, MD

Products

Geopier GP3® System

Ductile Iron Pipe Piles (DIP’s)

Additional Projects

The Yards at Three Crossing

Pittsburgh, PA

Eisenhower Avenue Soundwall

Alexandria, VA

Citterio Prosciutto Plant Expansion

Freeland, PA

North Carolina State University – Center for Technology & Innovation Parking Garage

Raleigh, NC

The Adele

Washington, DC

Costco

Oceanside, NY

Goliath Data Center (Cyrus One)

Sterling, VA

Dominion Greensville County Power Station

Emporia, VA

US Cold Storage Warehouse Expansion

Warsaw, NC

Navy Federal Credit Union Headquarters

Vienna, VA

Virginia Tech – Brodie Hall

Blacksburg, VA

Rowan University Rohrer College of Business

Glassboro, NJ

Grosvenor Heights

Bethesda, MD

Ambler Savings Bank

Ambler, PA

Village at Valley Forge

King of Prussia, PA

Home Depot

Cherry Hill, NJ

I-95 Express Lanes Post and Panel Walls

Prince William to Fairfax County, VA

Tappan Zee Hudson River Crossing

Nyack, NY

Fairfax County Public Safety Headquarters

Fairfax, VA

Rex Hospital Parking Garage

Raleigh, NC

Arlington Cemetery – Millennium Project

Arlington, VA

PortSouth Bryla Distribution Facility

Carteret, NJ

Potomac Yard Park North Pond Walls

Alexandria, VA

Court House Metro Plaza

Arlington, VA

Milton Wastewater Treatment Plant

Milton, PA

Walker Jones School

Washington, DC

Virginia Tech Rasche Hall

Blacksburg, VA

Howard University Residence Halls

Washington, DC

New Belgium Brewery

Asheville, NC

Martha Jefferson Hospital Replacement Campus

Charlottesville, VA

Joseph C. Scott Medical Center Addition at Rydal Park

Rydal, PA

Hershey Medical Center Centerview Parking Garage Phase II

Hershey, PA

NC Specialty Hospital

Durnham, NC

Advanced Technology Research Facility – Frederick National Laboratory for Cancer Research

Frederick, MD

Specfuel Waste to Energy Plant Addition

Philadelphia, PA

Chobani Plant and Distribution Facility

New Berlin, NY

Spirit Aerosystems Composite Manufacturing Facility

Kinston, NC

Chatham Industrial Park Bebo Bridge

Fredericksburg, VA

Castle Oil Storage Tanks

Bronx, NY

Refinery

N/A

Rappahannock Regional Jail Expansion Retaining Wall

Stafford, VA

The United States Air Force Memorial

Arlington, VA

P-132 SOF Cafeteria – NAS Oceana, Dam Neck Annex

Virginia Beach, VA

Highspire Wastewater Treatment Plant Upgrade

Borough of Highspire, PA

Lehigh County Authority Flow Equalization Tank

Allentown, PA

FDA SE Quadrant Laboratories and Office Buildings 71 and 75

Silver Spring, MD

University of Mary Washington Dormitory (Eagle Village)

Fredericksburg, VA

Virginia Commonwealth University – Monroe Park Campus Dormitory and Parking Garage

Richmond, VA

Western PA School for the Deaf New Dormitory

Pittsburgh, PA

Boyce Middle School

Pittsburgh, PA

Towson University Liberal Arts Building – Phase II

Towson, MD

Augustine North Section 10 Omega Arch

Stafford County, VA

Holiday Inn Express

Alexandria, VA

East King Street Redevelopment – Eastside Flats

Malvern, PA

Westminster Place at Carroll Village

Dillsburg, PA

TownePlace Suites by Marriott

Frederick, MD

Bethesda North Marriott Hotel and Conference Center

Rockville, MD

Sunrise at Fox Hill Assisted Living

Bethesda, MD

The Oaks at North Bethesda

Bethesda, MD

The Grays on Pennsylvania Avenue

Washington D.C.

Yale Steam Laundry Building 1 Condominiums

Washington D.C.

Virginia Tech Basketball Practice Facility

Blacksburg, VA

PPG Paints Arena

Pittsburgh, PA

Riverhounds Events Center – Highmark Stadium

Pittsburgh, PA

Cattaraugus Community Sports Complex

Irving, NY

The Hockessin Athletic Club and Parking Deck

Hockessin, DE

Riggs LaSalle Recreation Center

Washington D.C.

Richmond International Airport

Richmond, VA

I-495 Capital Beltway Slope Enhancement – HOT Lanes

Fairfax, VA

KIPP DC: LEAP Academy

Washington D.C.

Capital One Headquarters – Post and Panel Wall

McLean, VA

Mosaic at Merrifield – Parcel B

Falls Church, VA

Western Wake Expressway (Triangle Expwy SR540)

Apex, NC

Village at Leesburg – Cobb Theater

Leesburg, VA

Target Store Slope Repair

Raleigh, NC

Baltimore Washington Parkway Slope Repair at Route 197 Exit

Laurel, MD

FDA East Access Road

Silver Spring, MD

11th Street Bridges

Washington, DC

The Charlotte Midtown and The Metropolitan at Midtown

Charlotte, NC

Walmart Store #3701

Mount Olive, NC

Potomac Yard Park

Alexandria, VA

Station 650 (Landbay J)

Alexandria, VA

Sands Casino Resort

Bethlehem, PA

Naval Square Biddle Hall Annex and Townhomes

Philadelphia, PA

Bakers Centre Shopping Plaza

Philadelphia, PA

Target Rochester

Rochester, NY

Sunrise at Cresskill

Cresskill, NJ

Motiva Sewaren Terminal Expansions

Sewaren, NJ

Fort Totten Station

Washington, DC

Seafrigo Cold Storage Warehouse

Elizabeth, NJ

I-495 HOT Lanes Sound Wall

Metro, VA

Westfield Wheaton Costco

Wheaton, MD

I-395 HOT Lanes

Alexandria, VA

Additional Projects

The Yards at Three Crossing

Pittsburgh, PA

Eisenhower Avenue Soundwall

Alexandria, VA

Citterio Prosciutto Plant Expansion

Freeland, PA

North Carolina State University – Center for Technology & Innovation Parking Garage

Raleigh, NC

The Adele

Washington, DC

Costco

Oceanside, NY

Goliath Data Center (Cyrus One)

Sterling, VA

Dominion Greensville County Power Station

Emporia, VA

US Cold Storage Warehouse Expansion

Warsaw, NC

Navy Federal Credit Union Headquarters

Vienna, VA

Virginia Tech – Brodie Hall

Blacksburg, VA

Rowan University Rohrer College of Business

Glassboro, NJ

Grosvenor Heights

Bethesda, MD

Ambler Savings Bank

Ambler, PA

Village at Valley Forge

King of Prussia, PA

Home Depot

Cherry Hill, NJ

I-95 Express Lanes Post and Panel Walls

Prince William to Fairfax County, VA

Tappan Zee Hudson River Crossing

Nyack, NY

Fairfax County Public Safety Headquarters

Fairfax, VA

Rex Hospital Parking Garage

Raleigh, NC

Arlington Cemetery – Millennium Project

Arlington, VA

PortSouth Bryla Distribution Facility

Carteret, NJ

Potomac Yard Park North Pond Walls

Alexandria, VA

Court House Metro Plaza

Arlington, VA

Milton Wastewater Treatment Plant

Milton, PA

Walker Jones School

Washington, DC

Virginia Tech Rasche Hall

Blacksburg, VA

Howard University Residence Halls

Washington, DC

New Belgium Brewery

Asheville, NC

Martha Jefferson Hospital Replacement Campus

Charlottesville, VA

Joseph C. Scott Medical Center Addition at Rydal Park

Rydal, PA

Hershey Medical Center Centerview Parking Garage Phase II

Hershey, PA

NC Specialty Hospital

Durnham, NC

Advanced Technology Research Facility – Frederick National Laboratory for Cancer Research

Frederick, MD

Specfuel Waste to Energy Plant Addition

Philadelphia, PA

Chobani Plant and Distribution Facility

New Berlin, NY

Spirit Aerosystems Composite Manufacturing Facility

Kinston, NC

Chatham Industrial Park Bebo Bridge

Fredericksburg, VA

Castle Oil Storage Tanks

Bronx, NY

Refinery

N/A

Rappahannock Regional Jail Expansion Retaining Wall

Stafford, VA

The United States Air Force Memorial

Arlington, VA

P-132 SOF Cafeteria – NAS Oceana, Dam Neck Annex

Virginia Beach, VA

Highspire Wastewater Treatment Plant Upgrade

Borough of Highspire, PA

Lehigh County Authority Flow Equalization Tank

Allentown, PA

FDA SE Quadrant Laboratories and Office Buildings 71 and 75

Silver Spring, MD

University of Mary Washington Dormitory (Eagle Village)

Fredericksburg, VA

Virginia Commonwealth University – Monroe Park Campus Dormitory and Parking Garage

Richmond, VA

Western PA School for the Deaf New Dormitory

Pittsburgh, PA

Boyce Middle School

Pittsburgh, PA

Towson University Liberal Arts Building – Phase II

Towson, MD

Augustine North Section 10 Omega Arch

Stafford County, VA

Holiday Inn Express

Alexandria, VA

East King Street Redevelopment – Eastside Flats

Malvern, PA

Westminster Place at Carroll Village

Dillsburg, PA

TownePlace Suites by Marriott

Frederick, MD

Bethesda North Marriott Hotel and Conference Center

Rockville, MD

Sunrise at Fox Hill Assisted Living

Bethesda, MD

The Oaks at North Bethesda

Bethesda, MD

The Grays on Pennsylvania Avenue

Washington D.C.

Yale Steam Laundry Building 1 Condominiums

Washington D.C.

Virginia Tech Basketball Practice Facility

Blacksburg, VA

PPG Paints Arena

Pittsburgh, PA

Riverhounds Events Center – Highmark Stadium

Pittsburgh, PA

Cattaraugus Community Sports Complex

Irving, NY

The Hockessin Athletic Club and Parking Deck

Hockessin, DE

Riggs LaSalle Recreation Center

Washington D.C.

Richmond International Airport

Richmond, VA

I-495 Capital Beltway Slope Enhancement – HOT Lanes

Fairfax, VA

KIPP DC: LEAP Academy

Washington D.C.

Capital One Headquarters – Post and Panel Wall

McLean, VA

Mosaic at Merrifield – Parcel B

Falls Church, VA

Western Wake Expressway (Triangle Expwy SR540)

Apex, NC

Village at Leesburg – Cobb Theater

Leesburg, VA

Target Store Slope Repair

Raleigh, NC

Baltimore Washington Parkway Slope Repair at Route 197 Exit

Laurel, MD

FDA East Access Road

Silver Spring, MD

11th Street Bridges

Washington, DC

The Charlotte Midtown and The Metropolitan at Midtown

Charlotte, NC

Walmart Store #3701

Mount Olive, NC

Potomac Yard Park

Alexandria, VA

Station 650 (Landbay J)

Alexandria, VA

Sands Casino Resort

Bethlehem, PA

Naval Square Biddle Hall Annex and Townhomes

Philadelphia, PA

Bakers Centre Shopping Plaza

Philadelphia, PA

Target Rochester

Rochester, NY

Sunrise at Cresskill

Cresskill, NJ

Motiva Sewaren Terminal Expansions

Sewaren, NJ

Fort Totten Station

Washington, DC

Seafrigo Cold Storage Warehouse

Elizabeth, NJ

I-495 HOT Lanes Sound Wall

Metro, VA

Westfield Wheaton Costco

Wheaton, MD

I-395 HOT Lanes

Alexandria, VA